Use this guide alongside your drawing review. Open the Scope app.
Start with the drawing revision and the scope of work.
A mirror and shower enclosure takeoff is a record of the items, quantities and stated specifications needed for review. Begin by identifying the drawing revision and the sheets that describe the work. This fictional example uses A-401 and A-402, both Revision 02. It contains two bathroom mirrors tagged M-01 and one shower enclosure tagged S-01. The example teaches a review method; it is not a customer project or a fabrication drawing.
- A-401 provides the room references and a general note calling for adhesive mirror mounting.
- A-402 provides the mirror and shower enclosure dimensions. Its mirror detail calls for concealed cleats, which conflicts with the general note on A-401.
- Keep Revision 02 with each worksheet item so a later drawing issue can be reviewed separately.
Establish quantities from locations, then check the sizes.
A typical mirror elevation can describe the size of a mirror without proving how many are installed. In this example, the room references explicitly place M-01 in Bathrooms 101 and 102, one in each room. That supports a quantity of two. S-01 is listed once, in Bathroom 101. The dimensions below are stated values, not measurements taken from the scale of the illustration.
| Item | Locations | Quantity | Stated size | Source |
|---|---|---|---|---|
| M-01 · Mirror | Bathrooms 101 and 102 | 2 | 1200 × 900 mm | A-401 locations; A-402 size · Rev 02 |
| S-01 · Shower enclosure | Bathroom 101 | 1 | 1500 × 2100 mm | A-401 location; A-402 size · Rev 02 |
- Count locations and check for duplicated tags before accepting a quantity.
- Keep width, height and units together. A size of 1200 by 900 means little if the units are missing.
- Record the evidence for quantity separately from the evidence for dimensions when they come from different parts of the set.
Separate a drawing fact from a specification that still needs an answer.
A complete-looking row is not necessarily a complete specification. Neither sheet states the shower glass thickness or its mounting arrangement. Those fields stay open. M-01 has a different problem: the general note on A-401 calls for adhesive mounting, while the mirror detail on A-402 calls for concealed cleats. Recording either instruction as an uncontested fact would hide a decision the estimator still needs to make.
| Field | Evidence | Estimator action |
|---|---|---|
| M-01 mounting | A-401: adhesive mounting. A-402: concealed cleats. | Record the conflict and request confirmation of the applicable fixing detail. |
| S-01 glass thickness | Not stated in the example sheets. | Leave blank and request the missing specification. |
| S-01 mounting | Not stated in the example sheets. | Leave blank and request the installation detail. |
- Keep the missing S-01 thickness and mounting fields empty, with a note describing what needs confirmation.
- Attach both M-01 mounting references to the review note instead of choosing one because it appeared first.
- Check the full drawing set and any relevant specification or clarification before resolving a discrepancy. Do not assume that one note automatically takes precedence.
Record the review decision, including a decision to hold an item.
The estimator can confirm the example's quantities and stated dimensions while still withholding approval of the incomplete items. Here the recorded decision is to keep M-01 and S-01 in Needs review, identify the questions above, and wait for a documented answer. This is a useful review outcome: the worksheet makes the known scope and the unresolved information clear without presenting a guess as a drawing fact.
- M-01: quantity 2 and size 1200 × 900 mm checked; mounting conflict remains open.
- S-01: quantity 1 and size 1500 × 2100 mm checked; glass thickness and mounting remain open.
- When a clarification arrives, record its reference, update the affected fields and keep the estimator's correction distinguishable from the original proposal.
- If an item is excluded from the reviewed scope, record why. An excluded item should not silently disappear from the review history.
Approve the checked scope and verify the exported worksheet.
After the open questions have been resolved, the estimator can review the corrected items and approve the scope that is ready. Compare the resulting CSV or Excel worksheet with the approved items: tags, locations, quantities, units, dimensions and review notes should agree. An approved takeoff records a review decision; it is not an instruction to fabricate or proof that installation requirements have been satisfied.
- Check that any held or excluded item is handled deliberately before treating the worksheet as complete.
- Keep the drawing revision and the clarification references with the exported file.
- Use Scope's public sample to explore field-level evidence, then apply the same review discipline to an authorized project in your account.
Questions before you start
Does a typical mirror detail establish the quantity?
No. Check the locations and any schedule or plan references that establish the count. In this synthetic example, two explicitly listed rooms support two mirrors; the elevation alone does not.
What if two sheets give different mounting instructions?
Keep both references visible, record the conflict and seek the applicable detail or clarification. Do not silently choose a fixing method or approve an unresolved specification.
Can this example be used for fabrication?
No. It is a fictional teaching example with deliberately incomplete specifications. A reviewed takeoff also does not replace the project-specific checks and approvals required for fabrication or installation.